Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Scottish Power / Longannet Power Station
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
—
Facility scope
EngineeringAker Carbon Capture
Point source approachPost-Combustion Capture
CO₂ concentration—
Flue gas pressure—
Compressor nameplate—
Compression stages5
Compression inlet—
Compression discharge473 psia
Description
In March 2010, the Scottish CCS (Carbon Capture & Storage) Consortium began an extensive Front End, Engineering and Design (FEED) study to
assess what exactly would be required from an engineering, commercial and regulatory, perspective in order to progress the CCS demonstration project at Longannet Power station in Scotland (Goldeneye) through to construction. The study has yielded invaluable knowledge in areas such as cost, design, end-to-end CCS chain operation, health and safety, environment, consent and permitting, risk management, and lessons learnt.
Southern Company / Plant Daniel
CO₂ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
79MW
CO₂ concentration
—
Facility scope
EngineeringLinde Engineering (ISBL), Southern Company Services (OSBL)
Point source approachPost-Combustion Capture
CO₂ concentration—
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge—
Description
Southern Company Services, with Linde Gas North America, is conducting a FEED study for a commercial-scale CO₂ capture system using Linde-BASF’s advanced aqueous amine technology at an NGCC plant of at least 375 MWe. The project will evaluate Alabama Power’s Plant Barry and Mississippi Power’s Plant Daniel to select the optimal host site, define project requirements, optimize process design, and deliver engineering packages along with a cost and schedule estimate within 15% accuracy. The study will build on prior feasibility work and site-specific testing.
Tampa Electric Polk Power Station Unit 2
CO₂ captured
3,420,780t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
4.5%vol%
Facility scope
EngineeringSargent & Lundy
Point source approachPost-Combustion Capture
CO₂ concentration4.5% vol%
Flue gas pressure14 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge—
Description
Tampa Electric Company, with ION Clean Energy, Sargent & Lundy, Koch Specialty Plant Services, and Siemens Energy, completed a FEED study to retrofit post-combustion CO2 capture onto Unit 2 of the Polk Power Station, a 1,190 MWe (1,168 MWe net) 4x4x1 natural gas combined cycle plant in Mulberry, Florida. Using ION Clean Energy's ICE-31 advanced solvent across two parallel capture trains, the design targets at least 95% capture, nearly 3.7 million tonnes of CO2 per year, with downstream Siemens compression and dehydration and integrated pipeline transport to dedicated Class VI geologic storage. Each train includes a direct contact cooler, absorber, stripper, and compression, with the absorber columns sized to support 1x1 operation at 75% combustion turbine load to preserve dispatch flexibility. The study was funded under DOE Award DE-FE0032224 and produced an AACE Class 3 (-20%/+30%) capital cost and cost-of-capture estimate.